Implementation of construction and installation works and equipment of building: Two-story annex for four kindergarten groups to the 61 Motley Rooster Kindergarten, SLP II – ‘to kindergarten’, plot 60, area Hristo Smirnensky-Slatina, district Slatina, city of Sofia
Employer: Sofia Municipality, Slatina District
Contractor: PSP EOOD
Started on: August 08, 2014
Completed: August 17, 2015
Total value of the contract: BGN 1 249 417.57 VAT excluded
Total built-up area of building: 1 183.00 m2
Contract performance includes dredging, formwork, reinforcing and concrete works before the construction of the annex, construction of water supply and sewerage systems, installation of heating and ventilation systems, construction of the following: high voltage, low voltage lighting systems, telephone, computer, TV networks, answering systems, fire alarm system, lightening protection and earthing systems, laying insulation system for exterior walls, supply and installation of window frames, entire interior finishing, equipping the building with furniture, appliances and equipment securing the implementation of education and entertainment process in kindergarten, implementation of a new organization of green areas and planting. Construction of 14 playgrounds for kindergarten and crèche groups (shock-absorbing pavement and supply and installation of playground equipment).________________________________________
VIDEO